Installation of 33kV Cable Circuit and 11kV Cable Circuit from Holbeach 33/11kV Primary Substation to Whaplode
Doocey Group on behalf of Western Power Distribution have completed the successful installation of an 11kv & 33Kv cable circuits in Holbeach area of Lincolnshire. This installation consisted of 13.8km of 33Kv and 3.5km of 11Kv cabling being installed in the area to continue Western Power Distribution investment in their networks to ensure future resilience to growing demand.
The successful delivery of this project was attrributed to the excellent project team from both Doocey Group and WPD who worked collobratively to ensure a seamless delivery. All challenges experienced on the project were overcome through good communication, professionalism and teamwork.