New Triple 11KV Circuits for National Grid at New Cross Hospital, Wolverhampton
Project Update
Doocey Group continue to deliver a first-class service on behalf of our long standing client National Grid Electrical Distribution in the urban area of Wolverhampton for a key customer the NHS Trust.
Doocey Group were successful on the award of the new triple 11KV circuits that has seen HV circuits been laid under a directly lay methodology from a NGED primary substation to the newly constructed wing extension of the New Cross Hospital Wolverhampton.
Works are currently ongoing and projected to be completed in the coming months that if the seamless delivery continues will see the crucial key date been active 4 weeks ahead of contractual programme.
The energisation of these vital circuits will support the community of Wolverhampton within the geographical area the Doocey Group business was originally conceived and commenced its journey in the Civil Engineering industry.
• Length of excavation – 5.2km
• Linear meterage of HV cables installed – 7.6Km
• No of circuits installed – 3 No.